Professional Practice


LAWS
P.D. 223 : Creation of the PRC
LOI 1000 : Guide to the Establishment of Professional Organizations
R.A. 545 : Act to Regulate the Practice of Architecture in the Philippines (2004)
R.A. 9266 : Architecture Act of 2004
R.A. 9285 : Alternative Dispute Resolution of 2004



ARCHITECT-OF-RECORD: has direct and professional responsibility
ARCHITECT-IN-CHARGE OF CONSTRUCTION: in charge of construction supervision
CONSULTING ARCHITECT: has recognized expertise or specialization

CERTIFICATE OF REGISTRATION
Grounds for Non-Issuance:
1.       Moral Turpitude (Criminal Acts)
2.       Immoral or Dishonorable Conduct
3.       Unsound Mind
Grounds for Revocation:
1.       Unauthorized Signing of Contracts
2.       Paid to secure COR
3.       Impersonation
4.       Aid in the practice of unauthorized persons
5.       Solicited projects without service / contract agreements
6.       Violations of the Act and its IRR



METHODS OF SELECTION
1.       Direct Selection
→ used for residential projects
2.       Comparative
→ used for institutions, corporations, or public agencies
3.       Design Competition
→ civic or monumental projects

METHODS OF COMPENSATION
1.       Percent of Project Construction Cost
2.       Multiple or Direct Personnel Expenses
→ Fee = ((manhour x rate)(multiplier)) + reimbursable expenses
multiplier ranges from 1.5 to 2.5, depending on office set-up, overhead, Architect’s experience, and complexity of project
3.       Professional Fee + Expenses
→ Fixed cost, used for single-architect project series
4.       Per Diem + Reimbursable Expenses
5.       Lump Sum or Fixed Fee
→ used for government projects, more paperwork and time-consuming
6.       Mixed Methods of Compensation



PROGRESS OF PAYMENT
                5% initial payment
                                → based on owner’s budget
                +10% of total basic fee = 15%
                                → upon finishing Schematic Design Phase
                +20% of total basic fee = 35%
                                → upon finishing Design Development Phase
                +50% of total basic fee = 85%
                                → upon finishing Contract Documents
                +15% of total basic fee = 100%
                                → after construction
                                → 5% civil liability; 10% site inspection



DIRECT COST: includes materials, labor, consumables, equipment, subcontract work
INDIRECT COST: includes mobilization / demobilization, transportation, overhead, taxes, contingencies, and mark-up

TOTAL DIRECT COST = MATERIAL COST + LABOR COST
SUBTOTAL COST = TOTAL DIRECT COST + CONTINGENCY
                → contingency = 5% to 10%
FINAL COST = SUBTOTAL COST + CONTRACTORS’ PROFIT
                → contractor’s profit = 15% to 20%



PROJECT CLASSIFICATIONS
according to complexity:
according to building type:
Grp. 1: Simplest Utilization and Character
    6% of PCC for P50M or less
P50 – 100M : +excess @ 5%
P101 – 200M : +excess @ 4%
P201 – 500M : +excess @ 3%
P501M – 1B : +excess @ 2%
P1B up : +excess @ 1%

Grp. 2: Moderate Complexity
     7% of PCC for P50M or less

Grp. 3: Exceptional Character
     8% of PCC for P50M or less
houses special equipment
Grp. 4: Low Rise Residentials
     10% of PCC

Grp. 5: Monumental Bldgs and Facilities
     12% of PCC

Grp. 6: Repetitive Building
     1st @ 100%, 2nd @ 80%, 3rd @ 60%, rest @ 40%

Grp. 7: Repetitive Housing
     1st @ 10%
     2nd to 10th @ +60% for each additional
     rest @ fee of 10 +30% for each add’l

Grp. 8: Interior Design + Site Planning
     15% of PCC

Grp. 9: Renovations for Groups 1 to 5
     150% of basic fee

Grp. 10: Technical Expertise
SPP201
PRE-DESIGN SERVICES

PRE-DESIGN SERVICES: identifying factors to be used in the formulation of the architectural solution

SCOPE
1.     Consultation: consultation to Client for advice
2.     Pre-Feasibility Studies: getting analysis of relative information
3.     Feasibility Studies: detailed analysis based on the pre-feasibility study
4.     Site Selection and Analysis: evaluation and selection of the site
5.     Site Utilization and Land Use Studies: detailed analysis of the site
6.     Architectural Research: analysis of research for conclusion
7.     Architectural Programming: identifying horizontal and vertical requirements
8.     Space Planning: determining the size and configuration
9.     Space Management Studies: analysis of space requirements
10.   Value Management: minimizing negative effects of simplified operations
11.   Design Brief Preparation: statement of TOR and other necessary requirements
12.   Promotional Services: promotion for financial support, ARCHITECT STANDS ONLY AS OWNER’S REPRESENTATIVE
SPP202
REGULAR DESIGN SERVICES

SCOPE OF SERVICES

Project Definition Phase
→ define the project.
     → owner consultation
Schematic Design Phase
→ design the scheme.
     → program schedule, initial line drawings, SPPCC
Design Development Phase
→ develop the design.
     → drawings, outline specs, diagrammatic layout
Contract Document Phase
→ document the design.
     → 5 sets of CDs, technical specifications, bldg permit
Bidding or Negotiation Phase
→ bid for the design.
     → preparation of bid documents
Construction Phase
→ construct the project.
SPP203
SPECIALIZED ALLIED SERVICES

SERVICE
METHOD OF COMPENSATION/FEE
UAP DOC
SPP DOC
Architectural Interiors
                → planning of indoor / enclosed areas
12 – 20% of work cost
percentage of work
Acoustic Design Services
                → planning for sound transmission design
15 – 20% of work cost
depending on work complexity
Architectural Lighting Layout and Design
                → planning for light transmission
Depending on work complexity
depending on work complexity
Site Development Planning
→ planning for spaces surrounding a specific building in relation to the existing conditions
10 – 15% of work cost
depending on estimated civil work cost
Site and Physical Planning
→ planning of arrangement of vertical structures within a piece of land
FRDP: Framework Development Plan
CMDP: Conceptual Master Development Plan
*PMDP: Preliminary Master Development Plan
*DMDP: Detailed Master Development Plan
*physical layout including roads
based on type:
-    Industrial Estates: P5,000 for first 50ha
-    Subdivisions w/in urban areas: P3,000 for first 50ha
-    Subdivisions w/in non-urban areas: P2,000 for first 50ha
-    Subdivisions w/in mountainous non-urban areas: P3,000 for first 50ha

Comprehensive Design and Planning
                → non-physical and non-engineering components
                → Data Gathering à MDP à EIA
Multiple Direct Personnel Expense
Multiple Direct Personnel Expense
Historical and Heritage Conservation Planning1
                → R&D for historical and heritage conservation
Security Evaluation and Planning1
                → rating the security value of structures
Building Systems Design1
                → production of building components
Facilities Management Support1
                → ensuring proper function and maintenance of the building
Building Testing and Commissioning1
                → recommending a systematic process for the structural system and materials
Building Environment Certification1
                → development of a building environment rating system

Forensic Architecture1
                → scientific study on the well-being of the built environment
Building Appraisal1
                → placing appropriate value on the building
Structural Conceptualization1
                → conceptualization and arrangement of structural components
Preliminary Services1
                → services under SPP201
Contract Documentation and Review1
                → knowledge on contract documents, specifications, estimate and quantity survey, etc.
Post-Design Services1
                → services under SPP204, SPP206, SPP207
Dispute Avoidance and Resolution1
                → knowledge on the ADR Act of 2004 and its IRR
Architectural Research Methods1
                → knowledge on research, materials, building types, design trends, writing, and photography
Special Building / Facility Planning and Design1
                → knowledge on the planning and design process of facilities and communities
Building Components1
                → knowledge on building materials and construction

Management of Architectural Practices[1]
                → knowledge on architectural office management




SPP204A
FULLTIME SUPERVISION SERVICES

SCOPE:
1.     Quality Control
2.     Evaluation of Construction Work
3.     Preparation of Daily Inspection Reports
4.     Filing of Documents

PARTIES INVOLVED IN BUILDING DESIGN AND CONSTRUCTION:
1.     Owner: orders for the implementation of the project
2.     Architect and Specialist Consultants: renders plan and design services
3.     Contractors: performs construction work
4.     Work Delivery and Supervision Assistants

CLERK-OF-WORKS: assisting construction inspector
CONSTRUCTION SUPERVISION GROUP (CSG): normally recommended by the Architect, responds to administrative matters


SPP204B
CONSTRUCTION MANAGEMENT SERVICES

CONSTRUCTION MANAGER: hired by the owner to coordinate and supervise
FEE: 1.5 – 3% of PCC


SPP205
POST-CONSTRUCTION SERVICES

SCOPE OF SERVICES:
1.     Building and Facilities Administration
a.       Building Maintenance
b.       Grounds and Landscape Supervision
c.       Building Equipment Maintenance
d.       Business Development and Management
2.     Post-Construction Evaluation

METHOD OF COMPENSATION: 4% to 6% of gross rentals or monthly salary

SPP206
COMPREHENSIVE ARCHITECTURAL SERVICES

-          Covers Pre-Design Services, Regular Design Services, Specialized Allied Services, Construction Services, and Post-Construction Services

PROJECT MANAGER: member of the A+E Team
                FEE: 2 – 5% of PCC


SPP207
DESIGN-BUILD SERVICES

BY ADMINISTRATION
→ construction management and labor supervision
                FEE: 7% of PCC

BY GUARANTEED MAXIMUM COST
                → guarantees maximum cost of labor and materials
                                FEE: 10% OF PCC
                                > excess of over 10% will be shouldered by the Architect and Owner
SPP208
ARCHITECTURAL DESIGN COMPETITION


SPP209
PROFESSIONAL ARCHITECTURAL CONSULTING SERVICES

PFPA: Philippine Federation of Professional Associations
CBNE: Council for the Built and Natural Environment
PCA: Professional Consulting Architect
RLP: Registered and Licensed Professional

COMPENSATION OF A PCA:
1.       Per Diem or Hourly Basis
2.       Retainer
when PCA services are required at intervals
3.       Salary cost times multiplier, plus direct cost or reimbursable expenses
Fee = (Salary Cost x Multiplier) + Reimbursable Expenses
4.       Fixed / Lump Sum Payment
5.       Percentage of Total Project Cost
SPECIFICATIONS
-          a written document that provides information needed in construction which cannot be placed in the drawings.

TYPES OF SPECIFICATIONS:
-          Closed Specifications: fixed and unchangeable
-          Open Specifications: allows the use of a number of products
-          Reference Specifications: indicates a reference standard
-          Performance Specifications: installation requirements that the product must meet are given
-          Brand Name Specifications

BILL OF MATERIALS: prepared by the Contractor; summarization of materials regardless of work
COST ESTIMATE: prepared by the Architect; classified into work items for ordering and budgeting



GENERAL CONDITIONS

CONTRACT DOCUMENTS:
-          Agreement
-          General Conditions
-          Special Provisions
-          Specifications and Supplementary Specifications
-          Drawings

TYPES OF BONDS:
-          Proposal Bond: guarantee to enter into a contract if awarded
-          Performance Bond: guarantee to execute work accordingly
-          Payment Bond: guarantee to pay all obligations based on contract
-          Guarantee Bond: guarantee of workmanship quality for 1 year (30% of contract amount)

BIDDING DOCUMENTS:
-          Proposal: financial (project cost); technical (organization)
-          Tender Documents: construction drawings and specifications
-          Invitation to Bid
-          Bid Bulletin: additional information provided before the bidding date
-          Instruction to Bidders
-          Site Conditions
DURATION PERIODS
-          Notice to Proceed: within 7 days
-          Architect’s action on Contractor’s payment: within 15 days
Request for Payment should be once a month, less 10% for retention
-          Owner’s action on Approved Certificate of Payment: within 15 days
-          Period for which the Claim for Adjustment should be asserted: 15 days
-          Termination of Contract with Contractor: within 15 days
a written notice should be submitted to the Owner and Architect
-          Period for which the Claim for Extra Cost of subcontractor should be asserted: 10 days
-          Issuance of notice to begin, suspend, or resume work: 10 days prior
-          Issuance of Request for Owner-Furnished Materials: 10 days before use
-          Issuance of Request for Drawings: 2 weeks
-          Period of Issuance of Request for Time Extension (due to Non-Contractor causes): 15 days after occurrence of delay
-          Period of Rectification of Defects and Faults: up to 60 calendar days
will be at the Contractor’s expense; but if fault is non-contractor, it will be shouldered by the Architect
-          Release of Retention: within 3 months after final payment
-          Repairs and corrective works after final payment: within 1 year from work acceptance date; response within 5 days of owner’s without notice
REQUIREMENTS FOR ISSUANCE OF FINAL PAYMENT
-          Certificate of Building Occupancy (issued by Contractor)
-          Certification of Final Inspection (issued by Building Official)
-          3 copies of panel board and circuit directory
-          3 sets of as-built drawings
-          3 copies of equipment manuals
-          3 copies of keying schedule



[1] Method of compensation is Multiple Direct Personnel Expense

Comments